
| Home |
Connect!
Campaign |
Phase 1 Building Program |
FUMC Master
Plan |
FUMC
Web
Site |
|
April 16, 2012 Building Committee Report
(presented at Church Council Meeting)
The
following summarizes the Building Committee activities since March 20,
2012.
Welcome Center
All exterior demolition with respect to the new Welcome Center has been completed. These items include removal of tree trunk, canopy structure, and railings. All underground utility demolition is complete. This includes the water line at the front of Welcome Center. Select fill in three lifts has been installed. The complete building pad is ready for concrete work. Concrete crews are to mobilize on Monday, April 16th. Sanctuary The organ pipes, windows and miscellaneous items have been covered and protected. All necessary pews have been removed. The restroom and stairs have been demolished. The ceiling to the Narthex has been demolished. Brick work on the Chancel has begun.
|
|
MARCH
20,
2012
Building
Committee
Report (presented at Church Council Meeting)
|
|
February
26,
2012
Building
Program
Update
|
|
January 8, 2012 Building
Program Update
|
|
November 15 Building Committee Update 1. The following summarizes the Building Committee activities since October 18, 2011. 2. On October 19th, Marlin Fenn, Billy Cooke and Eric Paulsen presented our Building Project to District Board of Church Location and Building. The Board approved our Project and Financing Plan. 3. The Design Team has submitted the construction drawings for the Connection Center and the Parking Lot on 4th Street to the City of Katy for permitting. Our construction contractor, Fretz Construction, has started the bidding process for the set of documents as well. The design of the Sanctuary Roofing Package and the Education Building HVAC Modification Package should be completed this month. 4. The Building Committee has met several times over the last month along with our A/V Subcommittee and Interiors Subcommittee. The A/V subcommittee reviewed a proposal for A/V improvements and modifications from our A/V consultant Pro/Sound. This proposal is still under review. A recommendation from the A/V subcommittee will be made to the Building Committee after a coordination meeting has been held with Fretz Construction, Pro/Sound and Turner/Duran to ensure all costs and work are accounted for. The Interiors Subcommittee has selected the floor coverings, bathroom fixtures and partition colors; counter top finishes and paint colors. The Interiors subcommittee is also addressing cabinet and storage needs as well as reviewing options for treatments such as artwork for some of the walls. 5. The Building Committee has decided to start the construction after the first of the year. This will allow the HVAC modifications within the Education Building to take place after the LPS breaks for the summer. This change will not increase the construction contract time; therefore the construction cost will not be impacted. 6. The Building Committee authorized the Design Team to prepare construction plans for a parking lot on the site of Parsonage 2. The Committee will make a recommendation to the congregation to construct this lot instead of the parking lot along 4th street due to the proximity of the Parsonage 2 site to the Sanctuary and the Family Life Center. 7. The Building Committee received the environmental report prepared by ATC. We are working on a plan to mitigate the issues that were raised in the report. The new construction will be impacting some existing materials have contain lead and asbestos. 8. The committee is working with three lending institutions in order to develop our short term and long term financing plan for the project. We hope to have a good understanding of our terms by the end of November. 9. Fretz has asked if there are any local contractors who would be interested in bidding the contract. If so, please contact him. 10. The Committee will be taking the final proposal to the church in January because the final price from Fretz will not be in until December 6, more information will be available on environmental issues and the financing cost. 11. The committee predicts an early January groundbreaking after Church conference on January 8. Marlin indicated church offices were planning on move to Parsonage #2 in early December. 12.
A rough
estimate for a completion date
for all construction in June/July, 2012. |
|
October
2,
2011
Status
Report (report
given by Billy Cooke at Church
Services)
Good morning. It is my pleasure to give you an update on our Building Project. As a reminder, our Building Project consists of five major components, the Connection Center which will be constructed by expanding our Sanctuary to the north and to the east, Sanctuary Renovations to address line of sight issues from the balcony, choir loft and the pews, Additional Parking, Heating and Air Conditioning Improvements and the Replacement of Roofs on the Sanctuary and Education Building. As of last week, the Design Team is over half way thru the construction drawing phase, which means construction plans will be submitted for permitting the week of October 24th. We now have our construction contractor on board. Fretz Construction has been selected to build our project subject to the negotiation of a contract. Fretz will be provided construction documents the week of November 7th for final pricing. We expect to receive their Guaranteed Maximum Price the week of November 28th. Fretz has been and will continue to provide input on construction costs, construction phasing and constructability as we complete the drawings. The Building Committee’s next steps this month include meetings to discuss the phasing of the construction, selection of colors and finishes and to determine how we will address the line of sight issues in the sanctuary. As you can imagine we are getting very close to breaking ground for construction. Right now we are anticipating this to happen in late November or early December. There will be notices sent out prior to this event. Before we take this step though, we need to take a few more administrative steps with the District and the Church. Marlin and I are working to set a date to meet with the District Superintendent and the District Board of Church Location and Building to obtain approval of the project and the financing plan. In addition, we will be coming to our Congregation for the same approvals through a Church Conference. Currently we have a Conference set for December 4th. It is likely that we will be ready for the Congregation’s approval prior to the 4th. If that materializes, notices for the additional meeting will be sent out. You can find more information about the committee’s work on the Church’s website. If you have any questions, please call the church office and the staff can direct you to the right person. Thank you. Minutes from the September 28 meeting with Billy Cooke, Jack Duran and Fretz Construction may be viewed by clicking this link (PDF) |
|
August 29, 2011 - Status
Report
We have moved past two large hurdles over the last few weeks: selecting a General Contractor, and approval by the City of Katy Zoning Board. In addition to these milestones, we have several other activities in progress.
|
June
28,
2011
-
Status Report
|
|
March 23, 2011 Status Report
|
January
27,
2011
Status
Report
|